Tuesday, 12 April 2011

Happy Easter from Wates!


This week, all the local residents recieved a bunch of daffodils and an easter egg to say Happy Easter from Wates, and to thank them for all their patience whilst we commence with these works.


We are also handing out raffle tickets to the locals, for a chance for them to win 2 large 'celebration' easter eggs and flowers. The raffle prize draw will take place Thursday 21st April in the Community Centre.

Monday, 11 April 2011

Local Businesses around the area



Here are some of the local businesses and suppliers Wates have been using regularly whilst the Rose Tree Court project takes place, such as sandwich shops, bakeries, and post offices. As we are all about people, we aim to help locals any way we can, by using their services and supplying them with business, and also promoting their services to other organisations.

Friday, 8 April 2011

Bird boxes placed around the area



In order to help the environment and local residents in any way we can, we have placed bird boxes and feeders all around the area.

Monday, 4 April 2011

Substructure works commence



Building of Substructure by Barnsley Brickwork, in preparation for Beam & Block works.

Wednesday, 23 March 2011

Monday, 14 March 2011

Thursday, 10 February 2011

Site Team


Wates Team on site, (left to right) Richard Vause (Project Manager), Steph Cageao (Commercial Trainee), John Martin (Guiness Northern Counties), Alex Bellis (Business Administrator), Chris Kirk (Site Manager), Dan Rodgers (Quantity Surveyor).

Monday, 24 January 2011

Removal of Contaminated Ground by Sirius


Site contaminated with Asbestos, licensed Asbestos Removal company to remove all contaminated ground.

Wednesday, 19 January 2011







Sirius Remediation works progress on site.

BC - Before Commencement

5th January 2011
The works began today with our Contractor Sirius Remediation arriving on site to set up for their works.
Sirius will be working over the next 8 weeks to remove the top vegitation and dig down to the clay level.
They will also mark out the plots for each of the bungalows.

Friday, 7 January 2011

Dilapidation Survey





A Road Condition survey has been carried out prior to construction works starting.