Monday, 24 January 2011

Removal of Contaminated Ground by Sirius


Site contaminated with Asbestos, licensed Asbestos Removal company to remove all contaminated ground.

Wednesday, 19 January 2011







Sirius Remediation works progress on site.

BC - Before Commencement

5th January 2011
The works began today with our Contractor Sirius Remediation arriving on site to set up for their works.
Sirius will be working over the next 8 weeks to remove the top vegitation and dig down to the clay level.
They will also mark out the plots for each of the bungalows.

Friday, 7 January 2011

Dilapidation Survey





A Road Condition survey has been carried out prior to construction works starting.